The Crossroads

 

Update August 2021

Highway Code

Using the road – Road junctions (170 to 183) – THE HIGHWAY CODE (highwaycodeuk.co.uk)

Under the new Highway Code rules, motorists must give way to pedestrians crossing the road at junctions. It states:

  • watch out for pedestrians crossing a road into which you are turning. If they have started to cross they have priority, so give way

These new rules will have a bearing on the Crossroads. These will be discussed at Parish Council meeting with ECC Highways meeting in August.

Site Meeting 18th June

A site meeting was held on 18th June with: David Gollop and Tom Eng – Essex Highways;  Ben Cook – Independent Highways Consultant who carried out the Crossroads Feasibility Study for the Parish Council; Adrian Carden – Essex Highways Safety Officer; Cllr. Alan Goggin – ECC

Speed cushions had already been suggested and accepted for all four roads leading to the crossroads. Our meeting that morning was to discuss a possible improvement to pedestrian safety particularly around the Hoy. It had been suggested that there could be an increase of 90 cm to that footway.

However, it was made very clear at the meeting by Essex Highways, that it was accepted that the crossroads were non-compliant in current highway regulations due to historical factors. But that any alterations in terms of carriageway or footway at the crossroads, even on the grounds of what could be considered safety improvements, would result in the crossroads being ruled as non-compliant. Therefore, it would lay Essex Highways open to being sued should there be an accident as a result of an improvement.

For instance, it had been established that the maximum possible width we could extend The Hoy corner to was 90 cm. To be compliant it has to be 1.2m and even at 90 cm, wider buggies and mobility scooters could not use it safely and it would be ruled as non-compliant.

Currently the design and this is what will go out to Consultation to businesses and those residents who live near the Crossroads will be:

  • Four cushions at the approach to the crossroads from both The Bury and Colchester Road.
  • Two cushions at the approach to crossroads in Spring Road and Clacton Road.
  • Improved road markings using a specialist paint which can last up to 5 years.
  • Six-inch-high kerb stones outside the butchers and down to Stone Alley to deter parking.
  • There is to be signage warning motorists that there may be pedestrians in the road.

As a Parish Council it is not all that we had hoped for when the Feasibility Study was commissioned. We do however understand and realise that the options for our crossroads because of the necessity for Highway compliance are massively limited. The planned improvement and alterations are certainly a positive way forward. We should remind ourselves that they are the first major safety improvements to our crossroads after nearly sixty years of discussion!

The Parish Council with Essex Highways will be revisiting and evaluating the alterations in 2022. Meanwhile it is to be hoped that after the Consultation, the speed cushions, which are moveable so positioning can be altered, can be placed as soon as possible at the crossroads.

Update June 2021

A further meeting was held on 25th May with members of Essex Highways, Alan Goggin for Essex CC, and Ben Cook from BMSL Consulting Ltd, to discuss designs to enable pedestrians and those pushing buggies and using mobility scooters to walk around The Hoy corner in comparative safety. We think there is a possibility of a resolution but as was pointed out by Ben Cook, improvements to one area of the crossroads would possibly be at the detriment of another. It is now recognised that the crossroads which is described as a staggered junction with a bend is never going to be compliant with Highway Regulations, but there may need to be a trade-off in order to ensure pedestrian safety.

Another meeting is to be held shortly but this time with the Head of the Safety Team for ECC. It will be an on site meeting. It was pointed out to all those who attended the meeting on the 25th  May, hat any design put forward by the engineering team for the crossroads has to go before the Essex Safety Team and they could on safety grounds refuse to let it go forward. Hence the Head of the Essex Safety Team will be attending the meeting in June, as whatever design is put forward for consideration we want to ensure that it will have the agreement of the Essex Safety Team.

Updated May 2021

The Crossroads

Although the PC remain delighted that we have £30,000 of funding now allocated for improvements to the crossroads, the design shown to Councillors did unfortunately fall short of our requirement that there should be safety improvements for both drivers and pedestrians.

The Engineering team had focused only on driver safety. We therefore requested that they revisited the scheme again. This they have done, but have told us that it is not possible to widen the footway around The Hoy because of the layout of the junction. This as you may imagine, was not what the PC wanted to hear and although it was explained at length why it could not be done, we requested a meeting with EH’s Design Manager, their Highway Liaison Officer and Ben Cook who carried out the Feasibility Study for the PC in 2019.

The meeting was held on 5th May, it was constructive with several avenues additionally explored. More work is to be done by the Engineering Team and we meet again at the end of May. It may be that we put the speed cushions down for this summer which would at least would be a plus in moving forward with the some of the safety aspects of the crossroads, but we want it to be safe for pedestrians too.

Updated 16 April 2021.

Proposed ECC Scheme for the Crossroads

In the March Parish Council Meeting (via Zoom), the ECC Highways design (that the PC is paying for!) for the crossroads was shown via a shared screen – the wonders of technology!!

Key elements of the proposed scheme:

  • Speed cushions on all four approaches to the crossroads.
  • Repositioning of some of the existing road markings.
  • Additional lighting on the Bury (opposite St Osyth Butchers).
  • The installation of 6” kerb stones outside and down from St Osyth Butchers.
  • The removal of an existing parking space in Clacton Road (to accommodate one of the cushions).
  • The possible installation of bollards in Spring Road opposite the Premier Store.

ECC have ruled ruled out many other suggestions such as traffic lights, raised platforms, priority changes, etc. for practicality, legal and technical reasons.     

While the councillors saw much to commend in the scheme, concern was expressed though at the omission of any form of pedestrian safety in the vicinity of The Hoy. The Feasibility Study had carefully considered how this might be achieved and the PC have requested that it is revisited with some urgency. The PC made it clear in 2019 that pedestrian safety was also a key issue.

The final design and scheme will go to Public Consultation, so residents will be able to see what is proposed and make comments.

March 2021

There is a lot happening with the Crossroads and we have created this item to keep Residents informed of developments.

Most of this information is from the Chairman’s Report, but we will add extra items as they come in. This will include accident reports.

Firstly, some clarifications about who is responsible to avoid any confusion. Primary responsibility for public roads lies with Essex County Council Highways. The Parish Council, however, provides input to ECC about the requirements of residents. Tendring District Council is not involved with the Crossroads directly.

March 2021

The local Highways panel for the Tendring District met on 18th March. It is this body of ECC Councillors and Essex Highways staff who meet and decide the funding for future highway projects for 2021/22 and our crossroads scheme is on the agenda. If you remember, the Parish Council paid for a Feasibility Study to be carried out a year ago looking for solutions to support both pedestrian and driver safety at the Crossroads. Several possibilities came from this. The Parish Council then worked with Essex Highways to consider a design integrating them . To  ensure the design was progressed, the Parish Council contributed £10,000 to ensure that the design phase of the crossroads was completed in preparation for the March 2021 meeting. Hopefully it will meet with a very favourable response and we know it will be fully supported by our County Councillor Alan Goggin who has worked with the Parish Council throughout. 

22nd March 2021: Success. There is now funding for the Crossroads! Wonderful!

Propo

Leave a Reply